Construction Progress Update - May 2025

Published on: May 28, 2025

As part of Tahoma Construction Services' commitment to delivering exceptional construction projects across the Pacific Northwest, we're excited to share our latest progress update on three major developments currently underway. Tahoma Construction Services, a subsidiary of Puyallup Tribal Enterprises, was created to handle the Puyallup Tribe's growing portfolio of construction projects while providing long-term construction jobs for tribal members. Our current projects—the Longhouse, Town Homes, and Cedar Wellness Center—showcase our dedication to quality craftsmanship, community development, and innovative construction solutions. This monthly update highlights the significant milestones achieved in May 2025 and previews the exciting work planned for June.

Construction site overview with project team

Work in Progress

Longhouse

  • Foundations & Slabs Complete
  • Log Deliveries have started (Two Trailers)
Log delivery for longhouse construction
Log delivery truckLogs being unloadedProject team at longhouse site
Heavy equipment and log handling
Log preparation and staging

Town Homes

  • Interior Finishes (Cabinets, Flooring, & Millwork, & Interior Painting)
  • Exterior Envelope (Siding, Roofing, Exterior Painting)
  • Concrete Driveways & Walks
Town homes construction progress
Town homes exterior progressTown homes roofing workTown homes siding installation
Town homes interior workTown homes final details

Cedar Wellness

  • Level One Demo
  • Metal Framing
  • Fire Suppression, Electrical, Plumbing, & HVAC Rough-In
  • 26th St - Temporary Parking Lot Improvements complete
Cedar Wellness construction progress
Cedar Wellness interior demolitionCedar Wellness metal framing work

Upcoming Work (June)

Longhouse

  • Crane & Equipment Deliveries (This week & Next Week)
  • Log Erection Starts Wednesday 5/28/25
  • North Civil work & west sewer underground work

Town Homes

  • Garage Doors, Mirrors, Shelving, Blinds, Shower Doors, Bath Accessories
  • Landscaping & Fencing start 6/2/25

Cedar Wellness

  • Insulation & Gypsum Wall Board
  • Low Voltage Rough-in